Aug 6 (Reuters) - The Canada Energy Regulator (CER) on
Tuesday said the Trans Mountain final interim tolls oral hearing
related to its pipeline expansion is scheduled to start on May
14 with final argument to take place in the summer of 2025.
Trans Mountain pipeline expansion (TMX) entered partial
operation in May, years behind schedule and at more than four
times the original cost.
TMX has had to raise tolls to recoup some costs. The
shippers are disputing the rate increase.
In April, the CER approved a request from shippers to
disclose additional detailed cost and expense information.
"The Commission adjusted the timeline proposed by the
parties, due to the increased volume and complexity of records
that must be assessed during this proceeding," the regulator
said in a statement.